220千伏辛堤頭變電站工程達標投產復檢意見.doc.doc
進入下載頁
為了貫徹落實國家電網公司國家電網基建[2005]255號《關于印發國家電網公司輸變電工程達標投產考核評定辦法(2005版)的通知》精神,根據開封供電公司《關于對220千伏汝陽(曙光)變電站工程達標投產復檢的請示》,河南省電力公司組織有關專家于2008年4月16日至17日在河南電網建設管理公司組織達標投產自檢基礎上進行了復檢。復檢情況報告如下:
一、工程概況
220千伏宋城(辛堤頭)變電站工程為新建工程,站址位于連霍高速公路與金明大道交口西南,占地面積約為30畝。建設規模為主變規劃容量:3×150兆伏安, 本期1×150兆伏安。220千伏出線規劃6回,本期2回,兩回出線為剖接開封火電廠∽杏花營變220KV線路,東剖接線由開杏線火電廠側進入220KV出線間隔自東向西數第一出線間隔,長度0.45千米;西剖接線由開杏線杏花營變側進入220KV出線間隔自西向東數第一出線間隔,長度0.75千米。110千伏出線規劃10回,本期3回。10千伏不對外出線,僅帶站用變和無功補償裝置。主變10千伏側配置2組7500千乏電容器。審定本工程概算總投資為6830萬元。
該站建設單位為開封供電公司,監理單位為河南立新電力建設監理有限公司,設計單位為鄭州電力設計院,土建施工為河南省第一建筑工程有限責任公司,線路施工為開封光利高科實業有限公司,電氣安裝為河南送變電公司,質檢單位為河南
To implement the State Grid Corporation of National Grid Infrastructure [2005] No. 255 "On the State Grid Corporation Transmission Project published Standards for the evaluation of production methods (2005 edition) to inform" the spirit of the power company under the Kaifeng "on the 220 kV Ru Yang (Dawn) substation project into production or review the compliance of Instructions ", Henan Electric Power Corporation has organized experts on April 16, 2008 to 17 in Henan power grid construction management organization achieving commissioning a re-examination based on self-test. Re-examination report is as follows:
First, project survey
220 kV Songcheng (h Dyke) works for the new project substation, station located at Highway and gold with Huo Ming Dao Jiaokou Southwest, an area of about 30 acres. Scale-based planning capacity variables: 3 × 150 MVA, Issue 1 × 150 MVA. 220 kV outlet planning 6 back, 2 back to this issue, the two return to qualify for the profile control access Kaifeng Thermal Power Plant ∽ xinghuaying change 220KV line, the East line of profile control wiring from the power plant to open apricot 220KV outlet side into the interval from east to west The first qualifying number interval, the length of 0.45 km; West profile control wiring from the opening line of apricot apricot camp changed the side into the interval 220KV outlet number from west to east the first qualifying interval, the length of 0.75 km. 110 kV outlet planning 10 back, 3 times the current period. 10 kV is not the external outlet, only with a station with a variable and reactive power compensation equipment. 10 kV side of transformer configuration group 2 7500 kvar capacitor. Validation of the project 概算總投資 to 68.3 million yuan.
The power station construction unit of the company in Kaifeng, Henan Lixin Power Management Unit Project Management Limited, design units for the Zhengzhou Electric Power Design Institute, civil construction works for the first limited liability company in Henan Province, Kaifeng, Mitsutoshi line construction for the Tech Industry Co., Ltd., Henan Electric Transmission and Distribution Company for the installation, quality control unit in Henan