        施工準備計劃

        我單位在漯平高速公路No.5合同段開工前的施工準備工作已擬定了詳細計劃,現呈交給貴辦,請貴辦審核并給予指導。
        詳細施工準備計劃安排如下:
        一、臨時房屋建設
        我單位已于2003年8月18日開始進行臨時房屋建設。由于施工現場附近沒有例行的住房可以租用,我單位研究決定將五標段項目經理部設在舞陽縣九街鄉王橋街東側,黃石公路與擬建高速公路之間,占地2畝,房屋全部采用活動板房,計劃在8月25日入住,并做好排污、排水設施。
        二、試驗室組建及試驗工作安排
        試驗室修建在項目經理部內,地板用素砼硬化,試驗室內部裝修。包括標養室,試驗室面積65平方米,采用活動板房搭建,計劃9月10日修建完畢。試驗儀器、設備計劃在9月20日配套安裝完畢。
        在我單位試驗室認證前,土樣試驗計劃委托漯河市公路局質檢站做填料取樣工作,根據九街鄉協調辦安排情況,進行取樣。待填料試驗
        Construction preparedness plans

        I units in the Luo section of Highway No.5 started before the construction contract has been developed to prepare detailed plans are submitted to your office, please do your review and guidance.
        Prepare detailed construction plans as follows:
        1, temporary housing
        My unit was on Aug. 18, 2003 to begin construction of temporary housing. As the construction site near the house can be rented there is no routine, I decided to five units of the Department of Lot Project Manager based in the east of Wuyang 9 parastic Wang Kiu, between Yellowstone Highway and the proposed highway, covering 2 acres Housing used in all portables, plans to stay on August 25, and make the sewage and drainage facilities.
        Second, the laboratory set up and test work
        Laboratory within the Ministry to build the project manager, floor hardening using plain concrete, laboratory internal decoration. Including the standard curing room, the laboratory area of 65 square meters, with activity board room set up, plan on Sept. 10 was completed. Test apparatus, equipment plans on Sept. 20 supporting installed.
        Certified laboratory in our unit before the trial soil samples Luohe City Highway Bureau commissioned to do quality inspection stations fill sampling, according to the arrangement in nine parastic Coordination Office to conduct sampling. When filling test
         