一、施工準備
1、明挖管道鋪設接口強度達到設計強度80%;
2、選定好砂、石子、水泥、磚、鋼筋等原材料,送樣到試驗室作原材料試驗,依據圖
紙要求進行試配,現場按照試驗室提供的配合比根據現場砂石含水量確定施工配合比。
二、施工方法
(一)、檢查井砌筑
1、井底基礎與管道基礎同時澆筑。
2、流槽一定與檢查井壁同時砌筑。表面用砂漿分層壓實抹光,流槽與上下游管道接順,
管內底高程符合混凝土管道基礎及安裝的允許偏差。
3、砌筑井室,用水沖凈基礎后,先鋪一層砂漿,再壓磚砌筑,做到滿鋪滿擠,磚與磚
間灰縫保持1cm。
4、與檢查井連接的所有管道端頭,要經過鑿毛處理并要清理干凈,保證管道與檢查井
井壁結合牢固。
5、砂漿拌和均勻,保證砌筑磚含水量為10~15%,砌體不得有豎向通縫,必須為上、
下錯縫,內外搭接。如井身不能一次砌完,在二次接高時,將原磚面上的泥土雜物清理干凈,
然后用水清洗磚面并浸透。
6、磚砌圓形檢查井時,隨時檢測直徑尺寸,當需要收口時,如為四面收進,則每次收
進不大于30mm;如為三面收進,則每次收進不大于50mm。砌筑檢查井的內壁應用原漿勾
縫,有抹面要求時,內壁抹面應分層壓實,外壁用砂漿搓縫并嚴實。
7、檢查井接入圓管的管口應與井內壁平齊,當接入管徑大于300mm 時,砌磚圈加固。
管子穿越井室壁或井底,留有30~50mm 的環縫,用油麻-水泥砂漿,油麻-石棉水泥或粘土
填塞并搗實。
8、砌筑井內踏步時,隨砌隨安,位置正確。踏步安裝后,在砌筑砂漿或混凝土未達到
規定抗壓強度前不得踩踏。混凝土井壁的踏步在預制或現澆時安裝。First, construction preparation
1, cut and cover pipeline Interface strength to meet the design strength of 80%;
2, good selection of sand, gravel, cement, bricks, steel and other raw materials, send samples to laboratories for testing raw materials, according to Figure
Test paper with the requirements, on-site laboratory provided in accordance with the ratio of water content determined according to the construction site sand and gravel mix.
Second, construction method
(A), check the well masonry
1, bottom pouring the same time base and pipeline infrastructure.
2, groove and inspection of certain masonry wall at the same time. Surface layer compaction trowel with mortar, tank and flow along the upstream and downstream channel access,
Pipe invert base line and installed concrete pipe tolerances.
3, masonry well chamber, the foundation of water rinse, Xian Pu layer of mortar, and then press brick building, so that at least covered with crowded, brick and tile
Between the mortar joint to maintain 1cm.
4, well connected with the inspection of all pipeline ends, to go through a hammer handle and to clean up the hair to ensure that pipeline and inspection wells
Combined with a solid wall.
5, uniform mixing mortar, brick masonry to ensure the moisture content of 10 ~ 15%, not a vertical straight joint masonry, must, on
The wrong slot, inside and outside the overlap. Such as the casing can not complete a puzzle, the second pick in the high, the original brick surface of the earth to clean up debris,
Then use water to clean the tile surface and soak.
6, circular brick inspection wells, the diameter of any test, shut up when needed, such as when incorporated into the four sides, then each received
Into not more than 30mm; the case of income into the three sides, is incorporated into each no larger than 50mm. Well masonry wall applications Check puree hook
Joint, there finishing requirements, wall finishing should be layered compaction, the outer wall with mortar joints and the tightly rubbing.
7, check the nozzle tube wells access should be flush with the wall Well, when access is greater than 300mm diameter, the brick ring reinforcement.
Tube through the well wall or bottom, left 30 ~ 50mm in girth, hemp oil - cement mortar, Yau Ma Tei - asbestos cement or clay
Filling and tamping.
8, when no progress masonry wells, with the puzzle with the security, the correct position. Stepping installed in mortar or concrete has not reached
Compressive strength requirement shall not be trampled before. Precast concrete wall of stepping in when the installation or place.