沖樁班防止偏孔質量技術交底內容:
根據造成偏孔的原因,在施工過程中采取以下防止措施:
1、根據甲方所提供的地質資料和相鄰的槽孔的地質情況,及時予知進入巖層的深度、夾層情況以及巖面的坡度,以便采取相應的措施;
2、保證樁架擺放準確,使錘心正對槽段中心線;加固樁架,減少沖錘過程中樁架的晃動;
3、沖錘的直徑控制在80-82CM之內,經常檢查錘牙的磨損程度,及時修補或更換;
4、沖孔過程中,提錘的高度控制2.5M之內,沖錘撞擊巖面時,保證鋼絲繩仍受拉力,以保持沖錘的豎直;
5、及時換漿,保持一定的泥漿濃度,防止粘錘;
6、沖孔至巖土分解面時,低錘密擊,直至進入巖層內部;
7、加強觀察,發現偏孔及時采取措施予以糾正。
Stone Pile class quality of technical disclosure to prevent the partial hole content:
According to the reasons causing partial hole in the construction process to take the following preventive measures:
1, according to the geological information provided by Party A and the adjacent slot of the geological conditions, in a timely manner to know the depth into the rock, mezzanine as well as the slope of rock surface in order to take appropriate measures;
2 post rack placed to ensure accurate to hammer heart is the center line of the trough section; reinforcement pile frame, reduce the hammer during the rock pile holder;
3, hammer of the diameter of control within the 80-82CM, regular checks of hammer teeth wear, timely repair or replacement;
4, punching process, provide a high degree of control 2.5M hammer within the hammer hit rock face, the guarantee still pull rope to keep the hammer in the vertical;
5, in time for slurry, the slurry to maintain a certain concentration, to prevent sticking hammer;
6, punching to the decomposition of surface rock, the low-density blow hammer until the rock into the interior;
7, to enhance observation, found that partial hole to take timely measures to correct.