袋裝砂井技術交底.doc
進入下載頁
交底內容:
1、 本工程袋裝砂井施工部位為非機動車道、人行道、綠化帶和邊坡,井徑為7cm,其施工間距為1米,正方形布置,具體按照技術部門繪制的布樁圖進行布置。
2、 施工機械為導管式振動打樁機;砂袋用聚丙烯編織袋;砂采用滲水率較高的中、粗砂,含泥量不應大于3%。
3、 施工工藝流程如下:
(1)整平原地面(2)攤鋪20cm砂墊層(3)測量放線:用小木樁定出每個樁位,測出砂墊層面高程(4)機具對準樁位(5)打入套管(6)沉入砂袋(7)拔出套管(8)埋砂袋頭
4、 質量要求:
(1) 允許偏差
Cards on the table contents:
1, the construction of Sand Wick Road construction sites for non-motor vehicles, sidewalks, green belts, and slope, well diameter of 7cm, the construction of distance is 1 meter square layout, specific technology sectors in accordance with plans drawn to pile layout.
2, construction machinery, pipe vibration pile driver; sand bags PP woven bags; sand with water seepage rates are relatively high, the coarse sand, mud content should not exceed 3%.
3, the construction process is as follows:
(1) The whole plain surface (2) Paving 20cm sand cushion (3) measurement and setting: using small wooden blocks set each pile location, measure the level sand pad elevation (4) Pile Alignment equipment (5) into the casing (6) sinking sand bags (7) pull the tube (8) head buried in sand bags
4, quality requirements:
(1) Tolerance