竹腳手架拆除工程安全作業交底.doc
進入下載頁
內容摘要:
1、 凡不符合高處作業的人員,禁止登高作業。并嚴禁酒后高處作業。
2、 嚴格正確使用勞動保護用品。遵守高處作業規定,工具必須入袋,物件嚴禁高處拋擲。
3、 強風區、雪天區、雨天區的環境,不準時行拆除作業。
4、 夜間拆除,必須布置良好的照明設備。
5、 拆除區或須設置警戒范圍,設立明顯的警示標記,非操作人員或地面施工人員,均不得通行或施工,安全員應配合現場監護。
6、 高層腳手架的拆除,應配備通訊裝置。
7、 拆除物件,應有垂直運輸機械安全輸送至地面,吊機不允許設在腳手架內。
8、 施工前應仔細檢查各結點、攀樁、傳動、索具等是否可靠,桿件必須二點捆扎吊運。
9、 拆除時,建筑內應及時關閉窗戶,嚴禁向窗外伸挑任何物件。
10、高層腳手架拆除,應沿建筑四周一步一步遞減。不允許二步同時拆除,或一前一后踏步式拆除,也不宜分立面拆除。如遇特殊情況,應有企業有關部門預先制定技術方案,經加固措施后,方可分立面拆除。
11、作業人員進入崗位后,應先進行檢查,如遇薄弱環節時,應先加固后拆除。對表面存留的物件,垃圾應先清理。
12、按下列順序進行拆除工作:安全網→擋笆→墊鋪笆→防護欄桿→擋腳桿→擱柵→斜拉桿→連墻桿→橫桿→頂撐→立桿。
13、立桿、斜拉桿的接長桿拆除,應二人以上配合進行,不宜單獨作業,否則易引起事故。
14、連墻桿、斜拉桿、登高設施的拆除,應隨腳手架整體
Abstract:
1, which do not meet the high operation, the prohibition of climbing operations. And non-work drink and height.
2, strictly correct use of labor protection articles. Comply with height job requirements, tools must be into the bag, thrown objects height is strictly prohibited.
3, strong wind area, snow area, wet area of the environment, when the lines are not allowed to demolition.
4, removed at night, good lighting to be arranged.
5, removal of area or areas shall be alert, warning marking the establishment of clear, non-operators or ground construction workers are not allowed to access or construction, with on-site security staff should be monitoring.
6, high-level scaffolding removed, should be equipped with communication devices.
7, removal of objects, should be perpendicular to the ground safe transport transport machinery, cranes are not allowed inside in scaffolding.
8, before the construction should be carefully examined each node, climbing poles, transmission, rigging and other reliability, two points must be tied bar lifting.
9, removal of, the building should be promptly closed the window, non-stretch to pick anything out the window.
10, high-level scaffolding removed, should be reduced step by step along the perimeter. At the same time does not allow two-step removed, or one after the other stepping-style demolition, should not be discrete surface removal. Under special circumstances, the relevant departments should be pre-established enterprise technology solutions, by strengthening the measures only after the removal of discrete surfaces.
11, operations officer to enter post, should first check, in case of weak links should be removed after the first reinforcement. Retention on the surface of objects, the garbage should be cleared first.
12, according to the following order removal of work: safety net block fence → → → protective pad shop fence railing foot pole → joists block → → → Wall oblique rod → rod → rod → top of support pole.
13, pole, pole removal of the access ramp rod should be carried out with two or more persons, not a separate operation, otherwise easily lead to accidents.
14, with walls, diagonal bar, climbing facilities shall be removed only with the overall scaffolding