交底內(nèi)容 瀝青灑布車作業(yè)
檢查機(jī)械、灑布裝置及防護(hù)、防火設(shè)備是否齊全有效。采用固定式噴燈向?yàn)r青箱的火管加熱時(shí),應(yīng)先打開瀝青箱上的煙囪口,并在液態(tài)瀝青淹 沒火管后方可點(diǎn)燃噴燈。加熱噴燈的火焰過大或擴(kuò)散蔓延時(shí)應(yīng)立即關(guān)閉噴燈,待多余的燃油燒盡后再行使用。噴燈使用前,應(yīng)先封閉吸油管及進(jìn)料口,手提噴燈點(diǎn)燃后不得接近易燃品。滿載瀝青的灑布車應(yīng)中速行駛。遇有彎道、下坡時(shí)應(yīng)提前減速,盡量避免緊急制動(dòng),行駛時(shí)嚴(yán)禁使用加熱系統(tǒng)。駕駛員與機(jī)上操作人員應(yīng)密切配合,操作人員應(yīng)注意自身的安全。作業(yè)時(shí)在噴灑瀝青方向10m以內(nèi)不得有人停留。
瀝青灑布機(jī)作業(yè)
工作前應(yīng)將灑布機(jī)車輪固定,檢查高壓膠管與噴油管聯(lián)接是否牢固,油嘴和節(jié)門是否暢通,機(jī)件有無損壞,檢查確認(rèn)完好后,再將噴油管預(yù)熱,安裝噴頭,結(jié)實(shí)在油箱內(nèi)試噴后,方可正式噴灑。裝載熱瀝青的油涌應(yīng)堅(jiān)固不得漏油,其裝油量要低于桶口10cm,向?yàn)⒉紮C(jī)油箱注油時(shí),油桶要靠穩(wěn),在油箱口緩慢向下倒油,不得猛倒。噴灑瀝青時(shí),手握的噴油管部分應(yīng)加纏舊麻袋或石棉繩等隔熱材料,操作時(shí),噴頭嚴(yán)禁向上。噴頭附近不得站人,不得逆風(fēng)扣作。壓油時(shí),速度要均勻,海里突然加快,噴油中斷時(shí),應(yīng)將噴頭放在灑布機(jī)油箱內(nèi),固定好噴管,不得滑動(dòng)。移動(dòng)灑布機(jī),油箱中的瀝青不得過滿。噴灑瀝青時(shí),如發(fā)現(xiàn)噴頭堵塞或其他故障,應(yīng)立即關(guān)閉閥門,等修理完好后再行作業(yè)。人工拌和作業(yè)應(yīng)使用鐵壺或長柄勺倒油,壺嘴或勺口不應(yīng)提行過高,防止熱油濺起傷人。
瀝青混合料拌和設(shè)備作業(yè)應(yīng)遵守下列規(guī)定:
(1) 作業(yè)前,熱料提升斗、攪拌器及各種稱斗內(nèi)不得有存料;
(2) 配有濕式除塵系統(tǒng)的拌和設(shè)備其除塵系統(tǒng)的水泵應(yīng)完好。并保證噴水量穩(wěn)定且不中斷。
(3) 卸料斗處于地下底坑時(shí),應(yīng)防止坑內(nèi)積水淹沒電器元件。
拌合機(jī)啟動(dòng)、停機(jī),必須按規(guī)定程序進(jìn)行。點(diǎn)火失效時(shí),
Clarification at the content of asphalt distributor operations
Inspection machinery, spraying equipment and protection, fire prevention equipment is complete and valid. With fixed blowtorch to heat asphalt tank fire control, it should first open the box on the chimney pitch and submerged in the liquid asphalt only after the fire lit torch tube. Heating torch's flame is too large or spreading should be immediately shut down burner, the excess fuel to be burned and then OK to use. Blowtorch before use, should be closed and the inlet suction pipe, hand-held torch lit not close to combustible materials. Loaded with asphalt sprayer car speed should be in the running. In case of corners, downhill should slow down early to avoid emergency braking, when driving is prohibited to use heating systems. Drivers and machine operators should cooperate closely, the operator should pay attention to its own security. Asphalt in the direction of spraying during operation shall not be less than 10m people remain.
Asphalt distributor machine operation
Work before spraying machine wheels should be fixed, check the high pressure hose is firmly connected with the fuel injection pipe, nozzle, and the door is smooth sections, parts for damage, check to confirm well, the then preheat fuel injection pipe, install sprinklers, solid spray in the fuel tank test only after a formal spray. Loading hot asphalt oil Chung should be strong no oil leakage, the equipment is lower than the barrel oil export 10cm, sump oiling to the sprayer, the oil drums to rely on steady, slow down pour in the oil tank mouth, not fiercely down. Spraying asphalt, the hand of the fuel injection pipe section should be added the old sacks or wrapped insulation materials such as asbestos rope, operation, nozzle upward strictly prohibited. Sprinklers shall not stand near the person may not deduct for wind. Oil pressure, the speed should be uniform, the sea suddenly speed up, fuel injection is interrupted, shall nozzle spraying oil on the box and fixed the nozzle, not sliding. Mobile spraying machine, asphalt tank not too full. Spraying asphalt, if found to nozzle blockage or other failure, the valve should be closed immediately, well before making such repair work. Artificial mixing operations should be used iron pot or dipper pour oil spout or spoon I should not begin a new line is too high to prevent the hot oil splashes hurt.
Asphalt Mixing Plant operations shall comply with the following provisions:
(1) before the operations, enhance the thermal material bucket, blender and all that shall not have kept fighting materials;
(2) Wet Cleaning System with mixing equipment, pumps its dust removal system should be intact. And to ensure stable and does not disrupt water spray.
(3) Discharge hopper at the end of pit underground, should prevent the accumulation of water flooded the pit electrical components.
Mixing machine startup, shutdown, must be conducted according to prescribed procedures. Ignition failure,