        安全交底內(nèi)容:
        1、 上下腳手架應(yīng)支斜道,不準(zhǔn)站在磚墻上砌筑、劃線、清掃墻面等工作;腳手架的高度(站腳處)應(yīng)低于砌磚高度。
        2、 嚴(yán)禁將過多磚塊集中堆放在飄塊、吊籠口等處。
        3、 砌磚使用的工具應(yīng)放在穩(wěn)妥的地方;工作完畢應(yīng)將腳手架上和磚墻上的碎磚、灰漿清掃干凈,以防掉落傷人。
        4、 禁止用手向上拋磚運(yùn)送,人工傳遞時(shí),應(yīng)穩(wěn)遞穩(wěn)接,兩人位置應(yīng)避免在同一垂直線上作業(yè)。
        5、 砍磚時(shí)應(yīng)面向內(nèi)打,以免碎磚落下傷人。
        6、 使用井架作垂直運(yùn)輸時(shí)不得超載,應(yīng)聯(lián)系好上落信號(hào),吊架平層穩(wěn)定后才能進(jìn)行裝卸作業(yè)。
        7、 超過胸部以上的墻面,不得繼續(xù)砌筑,必須及時(shí)搭設(shè)好架高工具,不準(zhǔn)用不穩(wěn)定的工具或物體在腳手架板面墊高工作。
        8、 夏季做好防雨措施,嚴(yán)防雨水沖走砂漿,致使砌體倒塌。
        Security cards on the table contents:
        1, up & down ramps should be supported, not allowed to stand on brick wall masonry, marking, cleaning walls, etc.; scaffold height (the foot station) should be lower than the brick height.
        2, is strictly prohibited to focus too much bricks stacked on floating blocks, hoists, mouth, etc..
        3, bricklaying tools should be on the safe areas; work should be completed and the scaffolding on the broken bricks and brick, mortar cleaned to prevent falling injuries.
        4, bricks thrown up against hand-delivery, artificial delivery, the delivery and stability should be stable then, the two should be avoided to work in the same vertical line.
        5, were playing for cutting brick should be so broken bricks fall injury.
        6, using the derrick shall not be overloaded for vertical transportation, should contact a good on and off signals, leveling hanger for loading and unloading operations can be stabilized.
        7, over and above the chest wall, shall not continue to masonry, must be promptly puts up a good frame of high tool, not allowed to use the unstable scaffolding tools or objects in the booster board work.