一、編制依據及編制原則
1編制依據
1.1 ###2標段招標文件
1.2 ###2標段施工圖
1.3施工現場勘察情況
1.4現行國家、省、市有關法律、法規、條例規定
1.5現行有關工程建設國家、行業、地方標準和強制性標準。
1.6ISO9001:2000質量管理體系
1.7ISO14001:1996環境管理體系
1.8OHSMS18001:1999職業安全健康管理體系
1.9山東省、濰坊市有關文件。
1.10同類工程施工經驗及工法匯編。
2編制原則
2.1施工總指導思想
本技術標作為指導施工的技術性文件,堅決遵守國家法律和強制性標準,嚴格履行向業主的承諾,堅持業主第一的宗旨,實現不斷完善產品質量和服務質量、滿足使用功能、消除質量通病的目標。編制時對工期、質量、環境保護、安全管理、服務、協調、文明施工目標、組織管理機構與施工組織、勞動力組織、施工進度計劃控制、機械設備及周轉材料配備、主要施工技術方案和技術措施、質量保證措施、安全保證措施、文明施工措施、環境保護措施、創兩型五化工地保證措施、推廣應用新技術等諸多因素做到充分考慮,突出其科學性、適用性和針對性、有效性、經濟性、制約性。以相應業主招標文件的要求。在施工前還要根據現場情況編制更加詳細的實施性作業指導書,用以組織和指導施工。
2.2工程各項管理目標
First, the preparation and establishment of the principle according to
A basis for preparing
1.1 # # # 2 Lot of tender documents
1.2 # # # 2 Lot Drawing
1.3 The situation of the construction site inspection
1.4 The existing national, provincial and municipal laws, regulations
1.5 State the existing construction, industry, local standards and mandatory standards.
1.6ISO9001: 2000 quality management system
1.7ISO14001: 1996 Environmental Management System
1.8OHSMS18001: 1999 Occupational Safety and Health Management System
1.9 Shandong Province, Weifang City, the relevant documents.
1.10 The experience of similar projects and construction methods of compilation.
2 Basis of preparation
2.1 Construction General guidelines
This technical standard as a guide the construction of technical documents, strictly observe the national laws and mandatory standards, strict compliance to the owner's commitment to uphold the purpose of the first owners to achieve continuously improve product quality and service quality to meet the use function, elimination of quality defects target. When the preparation time, quality and environmental protection, security management, service coordination, civil construction goals, organization and management institutions and construction organizations, labor organizations, the construction schedule control, mechanical equipment and working materials, equipment, major construction project and its measures quality assurance measures, security guarantees, civil construction measures, environmental protection measures, creating two types of five chemicals to ensure that measures to promote the application of new technologies to achieve full account many factors, highlighting the scientific, applicability and relevance, valid , economy, restrictive. The corresponding tender documents required the owners. Still under construction site conditions prior to the preparation of more detailed implementation of work instructions, to organize and guide the construction.
2.2 The project management objectives