一、施工部署:
由于本工程工期相對較短,我單位安排一個專業施工隊伍,負
責鋼筋混凝土煙囪施工。由于本工程工種較多,工程量與勞動力的配
備不可能完全均衡,因此,臺上、臺下均采取專業、混合相結合的綜
合勞動組織形式,強調分工協作。
1、工期安排
從基礎挖土到混凝土澆筑、回填土完畢,計劃用時105 天。其
中從±0 開始到筒身施工結束,計劃用時60 天。First, the construction plans:
As the relatively short duration of this project, I arranged a professional construction team units, negative
Responsible for construction of reinforced concrete chimney. As more of this type of work projects, engineering capacity and the labor force with
Equipment can not be completely balanced, so the stage, the audience are a professional, mixed comprehensive combination
Co-work organization, stress division collaboration.
1, time arrangement
From the foundation excavation to concrete placement, backfill is completed, plans to use the time 105 days. Its
± 0 from the beginning to the end of Silo body construction, plans to use about 60 days.