1、工程概況:
東華理工學院南昌校區位于南昌市新城區,該項目由東華理工學院投資、北方設計研究院設計,建筑面積9811平方米,總高度26.3米的三層建筑物。1F為綜合訓練場、健身房、乒乓球館,2F為輔助用房,3F為觀眾廳和比賽廳。
本安裝工程包括電氣(強電和弱電)、生活給排水、消防、防排煙工程。給水系統由校區給水網直接供水。主要包括:生活給排水、消防栓等。室內給水熱水用PP-R管、冷水用PP-B管熱熔連接,排水管采用U-PVC管,消防管采用焊接鋼管焊接連接,本工程的電氣安裝包括強電和弱電,強電包括:動力和照明、電氣設備安裝及防雷接地系統安裝。弱電包括:電話及綜合布線系統、有線電視系統、監控系統、廣播系統和火災自動報警及聯動等,諸多系統體現了大型現代化智能建筑功能齊全,自動化程度高的特點。該工程的各樓層房間均設置機械通風及排煙系統。
電氣弱電工程包括:綜合布線及消防報警。
2、施工部署及項目機構組織
2.1、施工部署:
根據本工程的特點,安裝工程合理安排施工人員, 按照“先下后上,先主管后支管,先干線后支線,先預制后安裝”的原則,實行平面分區、立體交叉作業的流水施工。為了給裝修及其他專業分包施工提供作業面,特別是水磨石地面施工前,安裝工程必須完成地面管線敷設、穿樓板的管道安裝及吊頂內安裝施工等內
1, Project Overview:
East China Institute of Technology campus is located in Nanchang, Nanchang new city, the project investment by the East China Institute of Technology, Design and Research Institute in northern design, construction area of 9811 square meters, total height of 26.3 m three-storey structure. 1F for the comprehensive training field, gymnasium, table tennis hall, 2F for the auxiliary building, 3F for the audience hall and games room.
The installation work, including electrical (electric and electronic), life water supply and drainage, fire, smoke control engineering. Water supply system directly from the campus water supply network. Include: life, water supply and drainage, fire hydrants, etc.. Indoor Water Supply PP-R pipe with hot water, cold water pipe with the PP-B melt connection, drainage pipe U-PVC pipe, fire tube welded steel pipe welded connection, the works of electrical installation, including electric and electronic, high power, including : power and lighting, electrical equipment installation and installation of lightning protection and grounding systems. Weak include: telephone and cabling system, cable TV systems, monitoring systems, broadcast systems and automatic fire alarm and so on, many systems reflects the large modern intelligent building full-featured, high degree of automation features. Rooms on each floor of the project are set to mechanical ventilation and smoke extraction system.
Weak electrical engineering including: cabling and fire alarm.
2, construction and project institutions and organizations to deploy
2.1, the construction plans:
According to the characteristics of the project, reasonable arrangements for the installation of construction personnel, in accordance with the "before you get on, after the first branch in charge, after the first trunk extension, after the first pre-install" principle, the implementation of plane partitions, construction of interchange operations flow. In order to decoration and other construction professionals to provide sub-surface operations, particularly before the construction of terrazzo floor, the installation must be completed pipeline laying the ground, wearing floor and ceiling to install pipes and other construction within the installation