第一章 工程概況 1
第二章 編制依據(jù) 6
第三章 項(xiàng)目經(jīng)理部組成 11
第四章 施工部署平面圖 14
第五章 施工進(jìn)度計(jì)劃及措施 17
第六章 施工方案 20
一、一般過(guò)程施工方案 20
二、特殊過(guò)程施工方案 34
三、關(guān)鍵工序施工方案 35
四、主要工藝流程 38
第七章 質(zhì)量安全保證措施 39
第八章 主要材料構(gòu)配件計(jì)劃 62
第九章 主要機(jī)械設(shè)備供應(yīng)計(jì)劃 63
第十章 勞動(dòng)安排 63
第十一章 文明施工 64
榆林市經(jīng)濟(jì)開發(fā)區(qū)管委會(huì)辦公樓
第一章 工程概況
1.1工程簡(jiǎn)介
榆林市經(jīng)濟(jì)開發(fā)區(qū)管委會(huì)辦公樓位于西沙210國(guó)道東側(cè),交通極為便利。建筑總面積為7450.38m2,設(shè)計(jì)單位為陜西城鎮(zhèn)規(guī)劃建筑設(shè)計(jì)研究院。
該工程地質(zhì)勘察報(bào)告齊全,"四通一平"完成,手續(xù)齊全,已具備開工條件,本工程抗震不設(shè)防,
Yulin Economic Development Zone Management Committee Office Building construction organization design
Directory
Chapter 1 Project Overview
Chapter 6, prepared according to
Chapter 11, the project manager form the Department of
Construction of the deployment of Chapter 14 Plan
Chapter 17 Construction Schedule and measures
Chapter 20 construction program
A general process of the construction program of 20
Second, the process of the construction program of 34 special
Third, the construction program of 35 key process
4, the main process 38
Chapter VII of the quality and safety assurance measures 39
Chapter VIII of the 62 major material components and parts scheme
Chapter 63 of the main machinery and equipment supply plan
Chapter 63 working arrangements
64 Chapter XI civilized construction
Yulin Economic Development Zone Management Committee Office Building
Chapter Project Overview
1.1 Project Description
Yulin Economic Development Zone Management Committee Office Building located at 210 State Road, east of Sea transportation is very convenient. The total construction area of 7450.38m2, design units for the Shaanxi Research Institute of Urban Planning and Design.
The engineering geological investigation report is complete, "a flat four-way" to complete the procedures are complete, the conditions already have started, the project seismic undefended,