淡水廠施工方案.doc
進入下載頁
臨時用水、電、氣管線及消防通訊設施的布置 第 1 頁 共 1 頁
4.5臨時用水、電、氣管線及消防通訊設施的布置
一、根據(jù)招標文件,業(yè)主提供管徑為100的施工用水接頭。施工、消防用水共用一個系統(tǒng),并設計量裝置,沿施工道路邊布置。在每個建筑物處留有接口,現(xiàn)場設2只室外消防栓。干管為φ100鋼管。
二、建筑物室內(nèi)配備適當數(shù)量的移動式消防滅火器材。
三、在臨時道路兩邊設置排水明溝,將場地雨水匯集,通過潛水泵提升排出場外。
四、施工用電已由業(yè)主從外網(wǎng)接入廠區(qū)內(nèi)。現(xiàn)場敷設電纜送到施工現(xiàn)場配電柜上、后根據(jù)施工需要分流到配電箱上。
五、施工用氧氣、乙炔、氬氣等采用市場上供應的瓶裝氣,施工用壓縮空氣利用移動式空壓機提供。
六、施工現(xiàn)場設置8門電話分支,并與xx_分公司現(xiàn)有電話網(wǎng)相連。
主要建構筑物施工 第 1 頁 共 1 頁
主要形象進度 第 1 頁 共 1 頁
5.1主要形象進度
一、淡水廠工程擬定從xx月xx日_場開始施工,交工時間
Temporary water, electricity, gas pipelines and fire communications facilities layout Page 1 of 1 page
4.5 temporary water, electricity, gas pipelines and fire communications facilities layout
1, according to tender documents, owners of the construction of 100 diameter water connection. Construction, a fire water sharing system and designed measuring device, along the side of the road construction layout. Left in each building office interface, the scene set two outdoor fire hydrant. Trunk pipe for the φ100.
Second, the building interior with an appropriate number of mobile fire fighting equipment.
Third, set up temporary road on both sides of the drainage ditch, the site rainwater collection, through the submersible pump to enhance off-site discharge.
4, construction electricity network from outside access by the owners of factories in the region. On-site laying cable distribution cabinet to the construction site, then under construction on the need to divert to the distribution box.
5, construction with oxygen, acetylene, argon, etc. supplied by bottled gas market, the construction used with compressed air to provide mobile air compressor.
6, the construction site set up eight telephone branch, and the existing telephone network with xx_ branch connected.
Construction of the main building structure 1 of 1 page
The progress of a main image of a
5.1 The progress of the main image
1, prepared from fresh plant projects _ field day xx xx months to start construction, the time for Completion