一、編制依據
龍門架及井字架物料提升機安全技術規(guī)范JGJ88-92,建筑施工扣件式鋼管腳手架安全技術規(guī)范JGJB-2001,SBA150型開門自鎖斷繩保護自升門式提升架安裝使用說明書。《建筑施工安全檢查標準》JGJ59-99河北省建筑施工安全檢查標準實施細則。
二、工程概況及安裝條件
本工程為唐山市宏揚花園商住樓工程,位于唐山市火炬路西側,由唐山宏揚房地產開發(fā)公司招標籌建,唐山國旺建筑安裝有限公司中標承建。工期為333天,要求2001年10月10日開工,2002年10月30日竣工交付使用。該工程由唐山市規(guī)劃建筑設計研究院設計,
1, prepared on the basis
Gantry and crosswise frame material hoist safety specifications JGJ88-92, construction steel tubular scaffold safety specifications JGJB-2001, SBA150-type self-locking door protection jack off rope elevator door frame installation instructions. "Construction safety inspection standards" JGJ59-99 Hebei Province, construction safety inspection standards implementation details.
Second, engineering survey and installation conditions
To carry forward this project in Tangshan City Garden composite construction, is located in Tangshan City, torch Road west, real estate development company from the Tangshan Hong Yang, tender preparation, construction and installation, Ltd. Tangshan Guo wang bid construction. Duration of 333 days, requested October 10, 2001 started on Oct. 30, 2002 completion of delivery. The project by the Tangshan City Planning and Design Institute of Design,