一、工程概況
本工程為唐山市宏揚花園商住樓工程,位于唐山市火炬路西側,由唐山宏揚房地產開發公司招標籌建,唐山國旺建筑安裝有限公司中標承建。工期為333天,要求2001年10月10日開工,2002年10月30日竣工交付使用。該工程由唐山市規劃建筑設計研究院設計,建筑平面為5單元組合條式住宅樓。建筑面積為16757.66M2(其中地下室面積2310M2)。地下是一層半地下室,地上主體為六層。地下室層高2.2M,首層層高為3.6M,二層層高為3.0M,三至六層層高為2.9M,單元組合為一梯兩戶,一二層為商業用房,三至六層為住宅。該工程為框架結構。腳手架拆除方案編制依據《建筑施工扣件式鋼管腳手架安全技術規范》(JGJ130-2001)、《建筑施工安全檢查標準》(JGJ59-99)、《河北省〈建筑施工安全檢查標準〉實施細則》等。
二、作業人員組成
腳手架拆除必須由持有上崗證的架子工拆除。設一名指揮人員架子工組長和架子工4名。
三、腳手架拆除順序
嚴格遵守拆除順序,堅持由上而下,先加固后拆的原則,不能上下同時作業, 拆除腳手
First, project survey
This works for commercial and residential project in Tangshan carry forward the garden, located in Tangshan City, Torch Road, west side, from the Tangshan Hong Yang, tender preparation of real estate development company, Tangshan Guo Wang Construction and Installation Co., Ltd. won the bid construction. Duration of 333 days, asked on Oct. 10, 2001 started on Oct. 30, 2002 completion of delivery. The project by the Tangshan City Planning and Design Institute of Design, Architecture flat strip combination for the 5 unit residential building. Construction area 16757.66M2 (including basement area of 2310M2). Ground is a layer of semi-basement, main floor for the six. Basement storey 2.2M, first floor storey to 3.6M, two-story story is 3.0M, three to six layers high as 2.9M, the combination of a ladder unit 2, a two-story commercial buildings, three to six-storey residential. The project for the frame structure. Scaffolding programming based remove "construction steel tubular scaffold safety technical specifications" (JGJ130-2001), "construction safety inspection standards" (JGJ59-99), "Hebei Province," Building and construction safety inspection standards for> the implementation details "and so on .
Second, the composition operation
Scaffolding removed must be held by appointment card Jia Zigong removed. Set a team leader and commander Jiazi Gong Jia Zigong 4.
Third, the order of scaffolding removed
Strictly abide by the removal order, uphold the top-down, after the demolition of the first principle of reinforcement, not up and down while operating, dismantling scaffold