寧波尚野服飾有限公司廠房工程活動房搭拆施工方案.doc
進入下載頁資料簡介
一、 水泥復合板活動房搭拆方案
本工程職工宿舍和辦公均搭設臨時活動房二層。搭設前按總平面布置選址,做好基礎的整平、夯實,鋪150碎石墊層,上澆C20砼150厚,四周設200×200排水溝。由專業安裝單位安拆,項目部管理。其技術措施必須做好以下各方面。
First, take the cement board house demolition program activities
The engineering staff quarters and office erection of temporary activities are two-story house. Before erection site by the general layout, good foundation leveling, compaction, laying of 150 hardcore, 150 thick concrete poured C20, 200 × 200 located around the drain. An installation by a professional demolition unit, the project managed by the Department. The technical measures necessary to do the following.
下載地址
