主廠房磚砌體抹灰工程作業指導書.doc
進入下載頁
主廠房磚砌體、抹灰工程作業指導書
一、 概況
1.1 ****二期主廠房磚砌體工程指A~D列1~19軸范圍內的所有砌筑、粉刷。包括汽機房12.6m以下的外墻、除氧煤倉間部分外墻、室內各功能分隔墻、屋面女兒墻等,屬于主廠房砼框架結構后的又一重要結構分部。
1.2 根據溫州地區有關規定,重點項目推廣使用蒸壓灰砂磚,為此本工程采用灰砂磚砌筑。經試驗比較,灰砂磚強度能滿足設計要求,容重略大于普通粘土磚,但不影響設計值。砌筑用砂漿為Mu7.5水泥砂漿。
1.3 除圖紙注明尺寸外,磚墻厚度均為240mm。本工程磚墻共約1000m3,墻面粉刷約10000m2,根據總體進度要求,3#機部分在4月底結束,4#機部分在6月底結束,絕對工期為6個月。
1.4 工程特點。本工程工作量較大,分布范圍廣,延用工期長,且處于結構與安裝交接階段,施工環境較復雜,墻體予留孔洞、預埋件較多。為了確保工程質量,各工作面合理交接,使整體工程順利進展,有必要對本砌筑,粉刷工程進行全面科學的控制、管理。
二、 施工準備
2.1 人員情況
本工程工作量較大,但實用工期偏緊,為確保進度,勞動力安排要相對集中,分層分部位進行突擊,人員安排如下表:
Main plant brick, plaster works operating instructions
I. Introduction
1.1 **** 2 main building brick works out that A ~ D range of 1 to 19 axes of all masonry, painting. Including the steam room 12.6m below the wall, between the part of the oxygen removal bunker wall, indoor functional barrier, roof parapet, etc., are the main factory building after the concrete frame structure is another important segment.
1.2 In accordance with the relevant provisions in Wenzhou, key projects to promote the use of autoclaved lime-sand brick, for the use of lime-sand brick construction projects. The test of comparison, sand-lime brick strength to meet design requirements, bulk density slightly larger than ordinary clay, but does not affect the design value. Masonry cement mortar was Mu7.5.
1.3 In addition to drawing size specified, the brick wall thickness are 240mm. The engineering brick wall of about 1000m3, wall painting of about 10000m2, based on the overall progress of the requirements of section 4 of Unit 3 at the end of Part 6 of Unit 4 at the end, the absolute duration of 6 months.
1.4 characteristics of the project. The workload of a larger project, wide distribution, continue to use the long construction period, and in the structure and installation of hand-over phase, the construction environment has become more complex, to leave holes in the wall, embedded parts more. To ensure quality, all face a reasonable transition to the smooth progress of the overall project, it is necessary to the masonry, painting works full scientific control and management.
Second, construction preparation
2.1 Persons
The workload of a larger project, but the practical tight schedule, to ensure the progress of labor arrangements should be grouped together, layering and conduct surprise site, arranged for the following table: