中央音樂學院附中遷建工程
卸料平臺施工方案
審核:
審定:
編制:
一九九九年十二月二十四日
一. 工程概況
中央音樂學院附中遷建工程綜合樓A區(qū),地下一層,地上十六層。周轉(zhuǎn)料投入為四層,為保證工程周轉(zhuǎn)料的順利使用,在主樓設一卸料平臺,以滿足工程施工的需要。
二. 卸料平臺的制作和使用
卸料平臺采用16#槽鋼制作,寬度為2.5米,長度為6.5米,上鋪5CM厚的木板,采用17的鋼絲繩拉錨,于結(jié)構(gòu)相連處采取在結(jié)構(gòu)頂板上予留100*100洞,采用鋼絲繩扣與之相連。具體的平臺制作和安裝見后附圖
High School reconstruction project of the Central Conservatory of Music
Unloading platform construction plan
Audit:
Validation:
Prepared by:
December 24, 1999
1. Project Overview
Central Conservatory Complex Building A relocation project area, basement, ground floor 16. Material inputs for the four working, working material to assure the smooth use of a discharge platform located in the main building to meet the construction needs.
2. Unloading platform of the production and use of
Unloading platform, a 16 # channel steel production, a width of 2.5 meters, 6.5 meters in length, capped 5CM thick wood, with 17 of the wire rope anchor, connected with the structure we adopted in the roof on the structure to stay in 100 * 100 holes, connected by rope buckle. Production and installation of concrete platforms see below photos