XX縣二水廠凈水廠施工方案.doc
進入下載頁
目 錄
一、施工方案
二、施工進度計劃及保證措施
三、平面布置
四、保證質量措施
五、保證安全措施
六、文明施工現場措施
七、勞動力安排計劃
八、主要材料、構件用量計劃
九、主要機具使用安排
十、合理化建議
一、施工方案
1-1工程概況、條件及特點
1工程概況
本工程是XX縣二水廠凈水廠合同編號為XX標段。水廠新建在XXX,廠區東西長162m,南北寬110m,占地面積26畝。廠區內自然地面標高在41.50¬-51.98之間,高差9.48m。根據現場勘察構筑物依地勢呈階梯布置,廠區地面控制標高為黃海高程48.0m最低處為41.3;從XX縣自來水公司原新墻河泵房,增設一條D
CONTENTS
A construction program
Second, the construction schedule and the assurance measures
III layout
Fourth, measures to ensure quality
Fifth, to ensure safety
6, civilized construction site measures
7, labor arrangement scheme
8, the main material, component usage plan
9, the main equipment used arrangements
10, rationalization proposals
A construction program
1-1 Project Overview, conditions and characteristics
1 Project Overview
This project is the second XX County Water treatment plant contract number for the XX tenders. Waterworks in XXX, plant east to west, 162m, north to south 110m, covers an area of 26 acres. Plant the natural ground elevation between the 41.50 ¬ -51.98, elevation 9.48m. According to on-site inspection of structures according to the terrain ladder arrangement, plant elevation of the ground control lowest point for the Yellow Sea Elevation 48.0m 41.3; from XX County, the new wall of the original river water companies pumping station, an additional D