一 施 工 方 案
編制依據(jù):XX師范學(xué)院東院教職工住宅(C棟)設(shè)計施工圖紙
XX師范學(xué)院東院教工住宅(18、19棟)工程招標書
招標答疑
建筑工程施工及驗收規(guī)范
本公司施工經(jīng)驗
現(xiàn)場實際情況
1. 1、工程概況
本工程為XX師范學(xué)院東院教職工住宅樓(C棟)工程。位于XX市XX師范學(xué)院生活區(qū)院內(nèi),由XX設(shè)計有限責(zé)任公司設(shè)計。建筑面積為5497.7m2,其中四室兩廳共36套,每套152.7m2,復(fù)式磚混結(jié)構(gòu),共三個單元,總長為73.54m,寬為14.94m,標準層:六層,層高均為2.80m,架空層為雜物間及車庫,層高分別為1.95m和2.55m,檐口高度為18.99m和19.25m。
1.1.1、建筑概況
本工程為三個單元呈一字型平面布置,每戶由四室二廳一廚二廁二陽臺組成。
1 、樓地面:
客廳、臥室、餐廳、陽臺、樓梯間地面為水泥砂漿壓光,廁、廚為250×250防滑地磚樓面。貯藏間為60mm厚砼地面,水泥砂漿面層,樓梯間踢腳線為水泥砂漿踢腳線。
2 、內(nèi)墻面、天棚:
所有天棚均為為水泥砂漿打底,“904”仿瓷涂料三遍。 廁所、衛(wèi)生間內(nèi)墻為水泥砂漿打底,面層200×300面磚到頂。其余內(nèi)
A work plan was implemented
Prepared according to: XX Normal University East Hospital Staff Housing (C Building) design and construction drawings
XX Normal University East Hospital faculty housing (18,19 Building) project tender
Tender Q
Building construction and acceptance
The company's construction experience
The actual situation on site
1.1, Project Overview
This works for the XX Normal University East Hospital Staff Residence Building (C Building) project. XX XX City Teachers College in living area hospital, a limited liability company by the XX design design. Construction area 5497.7m2, which Sishiliangting 36 sets, each set of 152.7m2, double-brick structure, a total of three units, a total length of 73.54m, a width of 14.94m, the standard level: six, floors are 2.80m, elevated floor utility room and garage floors were 1.95m and 2.55m, eaves height of 18.99m and 19.25m.
1.1.1, building profiles
This project was a font for the three units layout, household toilets by the Sishierting a kitchen and second balcony second component.
1, the ground floor:
Living room, bedroom, dining, balcony, staircase light ground pressure for the cement mortar, toilet, kitchen floor to 250 × 250 Fanghuadizhuan. Storage rooms for the 60mm thick concrete floors, cement mortar surface, stair baseboard skirting board for the cement mortar.
2, internal walls, ceiling:
All of cement mortar for the ceiling are bottoming, "904" three times melamine coating. Toilet, bathroom walls for the cement mortar primer, the surface layer 200 × 300 tile up to the ceiling. Remaining within