復(fù)合型保溫彩鋼板安裝方案.doc
進(jìn)入下載頁
(1)
加工壓制金屬板原材料應(yīng)有生產(chǎn)廠商的質(zhì)量證明書,對(duì)原材料的品質(zhì)按有關(guān)規(guī)定做抽樣檢查,其結(jié)果應(yīng)符合國(guó)家現(xiàn)行標(biāo)準(zhǔn)的規(guī)定或定貨合同的要求。
壓型金屬板和泛水板、包角板成型后,其基板不得有裂紋。
加工時(shí)要避免出現(xiàn)漆模裂紋剝落和露出金屬基板等缺陷。
(2)
壓型金屬板后按合同文件的要求包裝出廠,包裝必須可靠,避免損傷壓型金屬板。
每個(gè)包裝箱均應(yīng)設(shè)置標(biāo)簽,標(biāo)明壓型金屬板的材質(zhì)、板型、板厚、板長(zhǎng)、板號(hào)、數(shù)量、和生產(chǎn)日期。
(3)
裝卸無外包裝的壓型金屬板時(shí),應(yīng)采用吊具起吊,嚴(yán)禁直接使用鋼絲繩起吊。
壓型金屬板的長(zhǎng)途運(yùn)輸應(yīng)采用集裝箱裝載。
用車輛運(yùn)輸無外包裝的壓型金屬板時(shí),應(yīng)在車上設(shè)置襯有橡木膠墊的枕木,其間距不宜大于3000MM。
9.2.3.3現(xiàn)場(chǎng)制作、場(chǎng)內(nèi)運(yùn)輸與安裝
原材料進(jìn)入現(xiàn)場(chǎng)后,根據(jù)貨物清單認(rèn)真檢查,如發(fā)現(xiàn)任何質(zhì)量缺陷或數(shù)量的短缺,應(yīng)以書面形式通知制造商。
現(xiàn)場(chǎng)加工與車間預(yù)制具有相同的操作工藝和質(zhì)量要求。
金屬板及泛水板、包角板為了避免板面的任何損傷,應(yīng)做到以下幾點(diǎn):
①
屬板必須對(duì)方緊固以免相互滑移對(duì)板面涂層的破壞。
②
開金屬板必須用尼龍繩和專用提開工具。
③
板長(zhǎng)超過6M時(shí),每隔3M應(yīng)設(shè)一道尼龍繩。
④
每米尼龍繩應(yīng)設(shè)比板略寬的墊塊做支撐。
⑤
提開金屬板時(shí)每貨盤金屬板的數(shù)量不宜超過12張。
在安裝中,始終是粉筆線作出鉛孔及打自攻釘或拉鉚釘?shù)奈恢茫@可以保證板
(1)
Metal raw materials processing to suppress should have a certificate of quality manufacturers of quality raw materials to do spot checks according to relevant regulations, and the results should be consistent with current national regulations or orders the contract requirements.
Pressed metal panels and flashing plate, wrap angle plate after molding, the substrate may not have crack.
Processing mode when the crack to avoid paint peeling off and exposing the defects such as metal substrates.
(2)
Pressed metal plates in accordance with the contract documents upon the request of packaging factory, packaging must be reliable and to avoid injury-pressure metal plates.
Each box should be set to label pressure metal plate material, plate type, thickness, plate length, plate number, quantity, and production date.
(3)
Working without the pressure of outer metal plates should be used lifting sling, wire rope lifting direct use is strictly prohibited.
Pressed metal plates of long-distance transport should be containerized.
Transport vehicle without the pressure of outer metal plates should be set up in the car is lined with oak pad of the sleepers, the distance should be less than 3000MM.
9.2.3.3-site production, transportation and installation of floor
Raw materials into the scene, according to carefully check the list of goods, such as found in any number of quality defects or shortage should be notified in writing the manufacturer.
On-site pre-processing and plant operations with the same technology and quality requirements.
Metal plate and pan water board, including board angle board to avoid any injury, should do the following:
①
Is a board fastened to each other so as to avoid another slip on the plate surface coating damage.
②
Open metal plate must be special mention of nylon rope and open tools.
③
When long boards more than 6M, 3M shall have one every nylon rope.
④
Each Mini Long rope should be set slightly wider than the board's pads to do support.
⑤
Open metal plate provided for each pallet number plate not more than 12.
In the installation, always make a chalk line to play lead hole and tapping screw or pop rivets position, which can ensure the board