十五、雨期施工方案.doc
進入下載頁
1.編制依據
《北京××工程施工圖紙》
《北京××工程施工組織設計》
《施工現場文明達標管理規定》
2.工程概況
本工程建筑面積××m2,地上××層,地下2層,局部××層。建筑檐高××m,為全現澆剪墻結構。除樓梯間內隔墻厚180mm外,其余內外墻均為200mm厚。今年雨季施工的項目為主體及二次結構工程。
3.雨期施工準備工作
3.1組織準備
項目部位立雨季施工領導小組,組成如下:
組工:×××
副組長:××× ×××
成 員:××× ××× ××× ××× ××× ×××
3.2技術準備
雨季到來之前,組織有關人員按照方案要求進行技術交底,提出雨施計劃,為施工提供技術準備。
3.3材料準備
1. Preparation of the basis
"Beijing × × design drawings"
"Beijing × × construction organization design"
"Construction site compliance regulations of civilization"
2. Project Profiles
The project construction area × × m2, on the ground × × floors 2 underground levels, local × × layer. Building eaves high × × m, for the whole place shear wall structure. In addition to the stairway wall thickness of 180mm, the other interior and exterior walls are 200mm thick. Construction of the project during the rainy season this year as the main and secondary structural engineering.
3. Rain preparation of construction
3.1 Organization of preparation
Construction of the project site during the rainy season established the leading group, composed as follows:
Group work: × × ×
Deputy head: × × × × × ×
Members: × × × × × × × × × × × × × × × × × ×
3.2 Technical Preparation
Before the rainy season, were organized to carry out technical disclosure in accordance with program requirements, make rain facilities plan to provide technical preparations for the construction.
3.3 Material preparation