一、整體評(píng)價(jià):
220千伏汝辛堤頭變電站工程主變壓器,斷路器、隔離開關(guān)等一次設(shè)備安裝、試驗(yàn)技術(shù)指標(biāo)滿足相關(guān)規(guī)范及設(shè)計(jì)要求;監(jiān)控系統(tǒng)、繼電保護(hù)等二次設(shè)備安裝、調(diào)試合格,滿足相關(guān)規(guī)范及設(shè)計(jì)要求;后臺(tái)信息齊全、正確;通信系統(tǒng)暢通;所用交直流電源可靠,220千伏電能平衡誤差符合要求,測(cè)量表計(jì)正確;投運(yùn)以來,基本無設(shè)備缺陷,全站電氣設(shè)備運(yùn)行正常。
二、扣分情況
1、6.5項(xiàng):關(guān)口表校驗(yàn)合格證未歸檔。 扣0.5分
2、6.10項(xiàng):110千伏、10千伏電能平衡
An overall evaluation:
220 kV Substation Project Ru Xin Dyke main transformer, circuit breaker, disconnecting switch time equipment installation, testing specifications to meet the relevant specifications and design requirements; control system, relay protection and other secondary equipment installation and testing to meet the relevant specifications and design requirements; background information is complete and correct; communication system flow; the use of AC-DC power supply is reliable, 220-kilovolt power balance error to meet the requirements, Meters correct; put into operation since almost no equipment defects, the station's electrical equipment is running properly.
Second, the situation points
1,6.5 item: mark sheet verification certificate is not filed. Deduction of 0.5 points
2,6.10 entries: 110 kV, 10 kV power balance